Pipeline History

On November 16, 1973, through Presidential approval of pipeline legilation, Alyeska Pipeline Service Company received

permission to begin construction of the 800-mile trans Alaska pipeline, its pump stations and the Marine Terminal at

Valdez. The 360-mile road from the Yukon River to Prudhoe Bay was built, and construction of the Valdez Terminal was

begun in 1974.At the same time, work started on pump stations and the pipeline work pad.

The lengths of pipe were placed under the Tonsina River in March of 1975. Barely two years later-by March of 1977- all

pipe had been installed; and pump stations, the Terminal and essential communications systems were almost completed.

The first oil entered the line at Prudhoe Bay June 20, 1977 and reached Valdez on July 28. On August 1, 1977, the first

tanker load of North Slope oil left the Port of Valdez aboard the ARCO Juneau.

Pipeline

Facts

Length : 800 miles

Construction Period :

1974-1977

Pipe Specifications:

diameter 48"

minimum yeild strengths 60,000,

65,000,& 70,000 psi

wall thickness .462 inch & .582 inch

insulated with 4" fiberglass, factory-bonded to

galvanized steel jacketing

Capacity of filled pipeline 9 million barrels

Animal Crossings:

554, specially built

River and Stream Crossing:

34 major, 800 others

Mountain Ranges Crossed:

Brooks Range

Alaska Range

Chugach Range

Marker can be reached from Steese Highway (at milepost 8.4), on the right when traveling north.

Courtesy hmdb.org

Credits and Sources:

HMDB